NormalHydroelectric

SAO SALVADOR

Tocantins · TOCANTINS

Useful capacity

46.38 hm³

Reported

November 9, 2026

67.3% of useful capacity

Current fill

67.3%

of useful capacity

Normal

vs 7 days ago

+32.2 pp

gaining

vs 1 year ago

-13.9 pp

year-over-year

7-day trend

↑

rising

Drought context

Brazil drought →

Storage vs November average

110%of normal

67.3% now · 61.3% average (2 yrs)

Rainfall, last 3 months

Near normal

SPI-3 −0.06 · to 21 Oct 2026

Drought figures describe the ground around the reservoir, not its storage. Sources: Copernicus GDO (SPI-3).

Recent readings

DateFill levelVolume (hm³)
9 Nov 202667.3%31.2
8 Nov 202641.0%19
7 Nov 202645.0%20.9
6 Nov 202649.0%22.7
5 Nov 202645.0%20.9
4 Nov 202675.1%34.8
3 Nov 202669.0%32
2 Nov 202635.1%16.3
1 Nov 202655.0%25.5
31 Oct 202651.0%23.6
30 Oct 202665.0%30.1
29 Oct 202677.2%35.8

Catchment Weather

Past 30 days + 14-day forecast · Open-Meteo

On the map

Zoom out for the other countries we track · click one to open it

Loading map…

Technical specifications

Usable capacity46.38 hm³
OperatorONS
Coordinates12.835°S, 48.225°W
Data source:ONS – Operador Nacional do Sistema Elétrico·Last reading: 2026-11-09

Satellite imagery: Esri, Maxar, Earthstar Geographics. Map: Esri, HERE, Garmin, © OpenStreetMap contributors. 12.835°S, 48.225°W · Open in Google Maps

About SAO SALVADOR

As of November 9, 2026, SAO SALVADOR is at 67.3% of useful capacity, holding 31.2 hm³ of 46.38 hm³. Of the 853.93 hm³ total capacity, that is 3.7%. At this level the reservoir is within its normal operating range.

Over the most recent week on record the fill level has risen by 32.2 percentage points, and it is 13.9 points below its level on the same date a year earlier.

Across the readings we hold for SAO SALVADOR — 65 data points between November 9, 2025 and November 9, 2026 — the level has ranged from a low of 13.6% (August 28, 2026) to a high of 91.6% (October 2, 2026). On average the reservoir is fullest around October and at its lowest around August.

It is operated by ONS primarily for hydroelectric power. It lies within the TOCANTINS basin at 12.835°S, 48.225°W.